It’s been…

991 DAYS Since our last Lost Time Injury

Categories : Days Without Injury
Comments (0)

Riverside Mine I.T. Office

Project: Riverside Mine I.T. Office
Client: BHP Billiton Mitsubishi Alliance
Location: Goonyella Riverside Mine
Brief: Design and Construct 1 x 36 Kilowatt Actron packaged unit and associated ductwork and controls. Including civil works.
Start date 9/2/2009 Target Completion 27/3/2009

Categories : Projects
Comments (0)

Project: Workshop 3 Supervisors Office
Client: BHP Billiton Mitsubishi Alliance
Location: Goonyella Riverside Mine
Brief: Design and Construct 2 x 16 Kilowatt Actron packaged units and associated ductwork and controls. Including civil works.
Start date 9/4/2009 Target Completion 27/5/2009 Total

Categories : Projects
Comments (0)

Single Persons Quarters

Project: Single Persons Quarters
Client: BHP Billiton Mitsubishi Alliance Moranbah Town Office
Location: Curtin House
Brief: Install 110 Fujitsu Split Systems
Start date 5/1/2009 Target Completion 9/2/2009

Categories : Projects
Comments (0)

Project: German Creek Wash Plant Administration Building
Client: Anglo Coal Australia (Capcoal)
Location: Middlemount
Brief: Decommission and remove existing end of life carrier packaged system and supply and Install 10 Fujitsu Split Systems. Replace existing Mechanical Services Switchboard,
Start date 9/2/2009 Target Completion 27/3/2009

Categories : Projects
Comments (0)

Executive Residence

Project: Executive Residence
Client: BHP Billiton Mitsubishi Alliance Dysart Town Office
Location: 6 Long Crescent Dysart
Brief: Replace existing end of life ducting on central ducted system.
Start date 1/7/2009 Target Completion 1/8/2009

Categories : Projects
Comments (0)

Riverside I.T. Offices

Project: Riverside I.T. Offices
Client: BHP Billiton Mitsubishi Alliance
Location: Goonyella Riverside Mine
Brief: Design and Construct 1 x36 Kilowatt Actron packaged unit and associated ductwork and controls. Including civil works.
Start date 9/2/2009 Target Completion 17/4/2009 Total

Categories : Projects
Comments (0)

Project: Goonyella Mine Wash-Plant Control Room.
Client: BHP Billiton Mitsubishi Alliance
Location: Goonyella Riverside Mine, Goonyella Rd Moranbah.
Brief: Design and Construct, Install test and commission the following equipment.
1 x Daikin 24 KW “VRV” 2 variable refrigerant volume system with 7 indoor units.
1 x Daikin 10 Kilowatt Sky-Air Under-ceiling unit.
2 x Daikin 7 Kilowatt Sky-Air under ceiling unit.
Start Date: 2/4/2007
Target Completion: 25/7/2004

Categories : Projects
Comments (0)

Riverside Train Loadout

Project: Riverside Train Loadout Clean Coal Substation
Client: BHP Billiton Mitsubishi Alliance
Location: Goonyella Riverside Mine, Goonyella Rd Moranbah.
Brief: Design and Construct 47 kilowatt Actron Packaged System and associated ductwork. Commission and provide 12 Months Service.
Start Date: 14/8/2008
Target Completion: 30/9/2008

Categories : Projects
Comments (0)

Wesfarmers Curragh

Client: Wesfarmers Curragh
Location: Curragh Mine Blackwater
Brief: Design and Manufacture Industrial Airconditioning units for Dragline 302. Fabricate and install ductwork to suit. Install and commission digital controls. Provide back-up service through defects liability period.
Start Date: 12/5/2008
Target Completion: 30/8/2008

Categories : Projects
Comments (0)